You can either fill in the form online below or download the form and send it back to us.
This notice is to be submitted to Building Control, at least 2 working days before work starts and within 5 days of work being regarded as commenced, under Regulation 15 of the Building (Registered Building Control Approvers etc.) (England) Regulations 2024.
A project is deemed commenced when:
For complex buildings – Foundations are constructed, and the structure of the lowest level is complete.
For new buildings and horizontal extensions – The sub-surface structure of the building or the extension including all foundations, any basement level (if any) and the structure of the ground floor level is completed.
For all other works – when 15% of the work has been completed specified by the person carrying out the work at the application stage.
This notice is submitted on behalf of the Domestic Client. “Domestic client” means a client for whom a project is being carried out which is not in the course or furtherance of a business of that client.